Why the hazard log matters
Under EN 50126, the hazard log is the central record of every identified hazard, its assessment, the measures taken to control it, and its current status. It is the thread that connects hazard analysis to safety requirements, safety requirements to design and test evidence, and all of that to the safety case. When an assessor wants to know whether a project is safe, the hazard log is usually where they start.
A weak hazard log is one of the most common reasons safety cases stall. The usual symptoms are hundreds of loosely worded entries, unclear ownership, and "closed" hazards with no evidence behind them.
Get the definitions right first
Many hazard log problems start with mixing up three different things:
- Cause: what could lead to the hazard, for example a failed track circuit or an incorrect data entry.
- Hazard: a condition that could lead to an accident, for example "train enters an occupied section".
- Accident (consequence): the harmful outcome, for example a collision.
Record hazards at the system boundary you are responsible for, and capture causes and consequences as linked attributes rather than as separate hazards. This keeps the log to a manageable size and makes risk assessment consistent.
Fields to record
| Field | What it captures |
|---|---|
| Hazard ID and title | A unique, stable identifier and a short, specific description |
| Description and context | The hazardous condition, operating mode, location or scenario |
| Causes | Linked causes, ideally referencing FMECA or fault tree items |
| Consequences | Credible accidents and who could be harmed |
| Source | Where the hazard was identified: workshop, analysis, incident, supplier |
| Initial risk | Severity and likelihood before controls, using the project risk matrix |
| Risk acceptance principle | Code of practice, reference system or explicit risk estimation |
| Controls | Each mitigation, traced to a safety requirement ID |
| Verification evidence | The test report, inspection record or analysis that proves each control is in place |
| Residual risk | Risk after controls, and the justification that it is acceptable |
| Owner | The person accountable for managing the hazard to closure |
| Status and history | Current status, dates, and a record of every change |
| Transfer | Whether the hazard is exported to, or imported from, another party, with references |
A simple status workflow
Use a small number of statuses, each with written entry criteria, and make sure everyone applies them the same way. One workable set:
- Open: identified and recorded, not yet fully assessed.
- Assessed: causes, consequences and initial risk agreed; controls being defined.
- Controlled: controls defined and traced to safety requirements; verification pending.
- Closed: every control verified with evidence, residual risk accepted by the authorised person.
- Transferred: responsibility formally accepted by another party, with a reference to their record.
The test for "Closed" should be strict: a proposed mitigation, a design intent or a statement in a meeting is not closure. If the evidence cannot be pointed to, the hazard is not closed.
Managing hazards at interfaces
On multi-contractor rail projects, hazards most often fall through the gaps between systems: rolling stock and signalling, platform and train, civil works and operations. Good practice includes:
- An interface hazard analysis for each significant interface, with both parties participating.
- A formal transfer process, where the receiving party acknowledges each exported hazard in writing.
- Regular cross-contractor hazard reviews chaired by the system integrator or client.
- Operational and maintenance hazards transferred to the operator and maintainer at handover, with the controls they must maintain.
Keeping the log healthy
- Review on a cadence. Hold a hazard review at each design stage and before every lifecycle gate, not just before the safety case is due.
- Control changes. Treat the hazard log as a configuration-controlled record, with a change history for each entry.
- Trace both ways. From hazard to requirement to evidence, and back again. Orphaned requirements and untraced controls are both red flags.
- Avoid duplicates. Merge hazards that describe the same condition; keep a reference from the retired ID.
- Use the right tool. Spreadsheets work for small systems, but cross-linked tools make traceability between hazards, analyses and requirements far easier to maintain on larger projects.
What an assessor will check
Expect an independent safety assessor to sample hazards and follow them end to end: is the hazard credible and well described, is the risk assessment consistent with the project method, does each control trace to a requirement, is there evidence the requirement is met, and did someone with authority accept the residual risk? A hazard log built around those questions from day one makes the safety case far easier to write.
Need help with this on a live project? Our railway RAMS and system safety team does this work every day.
Start a conversationFURTHER READING
- Guidelines and lessons learned implementing a hazard log according to EN 50126
- TÜV Risktec: CSM-RA and EN 50126
Standards are summarised here for guidance. Always work from the edition and national adoption named in your contract.